Mission Critical Project
Palmetto, GA
NGP demonstrated its expertise in mission-critical infrastructure with this expansive data center project in Palmetto, Georgia. In just six months, our team efficiently cleared and prepared 120 acres, executed a massive 800,000 cubic yard excavation, and installed extensive utility systems including 9,200 linear feet of storm drainage and 6,400 linear feet of sanitary sewer pipes. The project's complexity was further showcased through the installation of 5,000 square feet of soil nail retaining walls and the placement of 41,000 tons of aggregate for pads and roadways. This comprehensive site preparation effort highlights NGP's ability to deliver large-scale, technically challenging projects with speed and precision, setting the stage for cutting-edge digital infrastructure.